Capital Projects
MENU
LOGIN
SEARCH
Menu Button
MENU
City Logo
Search Button
SEARCH

Projects Under Construction



City Project #18-69 - Surface Water Distribution System Improvements

The Project consists of constructing a 2.3 million gallon concrete tank, 12 million gallon per day pump station and building, detention basin and storm water pump station, 12,000 linear feet of 16-inch to 54-inch diameter potable water pipeline and appurtenances, 2,500 linear feet of 15-inch storm drain pipeline and manholes, three pressure reducing valve vaults, pavement improvements, associated grading, structural mechanical, electrical, and instrumentation equipment, and all work necessary to provide a complete and operational facility. A pre-bid conference will be held at 10:00 a.m., local time on Wednesday June 16, 2021 through a video conference and a second pre-bid conference will be held at 10:00 a.m., local time on Monday June 28, 2021 through a video conference. The pre-bid conference is mandatory and a bidder who fails to attend a pre-bid conference may be disqualified from bidding. Bidders only need to attend one pre-bid conference. To obtain video conference login information email all of the following contacts at least 24 hours prior to the pre-bid meeting date and time: Jonathon Marshall jpmarshall@carollo.com, Darren Baune dbaune@carollo.com, and Andrew Coulter acoulter@carollo.com to request the login information.

Construction Duration: Work for the following project is schedule to begin on or about Friday, September 10, 2021 and estimated to complete on or around Saturday, August 5, 2023.
Contractor: Mountain Cascade
Traffic Delays: Pipeline construction will include Zeering Road from Quincy Road to Wellington, Quincy Road from Zeering Road to Sebastian, Monte Vista Ave. from Quincy to Berkeley. Lane closures will be in effect for work on Monte Vista Ave. and Zeering Road. Road closures will be in effect for Quincy Road (local traffic only). In addition, the Stanislaus Regional Water Authority (SRWA) will be installing pipeline to the City's terminal tank site on Berkeley Road (north of City limits), on E. Taylor Road between Berkeley and Quincy, and on Quincy Rd. to the City's terminal tank site located at 3500 N. Quincy Road. For more information, please visit Stanislaus Regional Water Authority and Turlock Water
Technical Contact: Stephen Fremming, Principal Civil Engineer, 209-668-5417, sfremming@turlock.ca.us

City Project #16-60 - Linwood Ave ATP Improvements

The work consists, in general of: remove existing improvements, earthwork and grading, grinding and paving, curb, gutter, and sidewalk, rapid flashing beacon crossing system, striping, storm drain improvements, water and sewer services, fire hydrants, electroliers, fencing and other associated work.

Construction Duration: Work for the following project is schedule to begin on or about Monday, February 14, 2022 and estimated to complete on or around Thursday, June 30, 2022.
Contractor: Rolfe Construction
Traffic Delays: Lane and full road closures. Use detours.
Technical Contact: Randall Jones

City Project #20-031 - Hedstrom Road Rehabilitation

The work consists, in general of: remove existing improvements, install access ramps, storm drain improvements, pavement preservation, hot mix asphalt, striping and signage, fire hydrant, and other associated work.

Construction Duration: Work for the following project is schedule to begin on or about Wednesday, June 1, 2022 and estimated to complete on or around Wednesday, August 31, 2022.
Contractor: Dirt Dynasty
Traffic Delays: Lane and road closures. Detours will be in place.
Technical Contact: Randall Jones

City Project #20-032 - Chemical System Upgrades Project at RWQCF

The Project consists of constructing the following components at the Regional Water Quality Control Facility: 1. Demolition of the existing Chlorine Gas disinfection system. 2. Installation of a new Sodium Hypochlorite disinfection system. 3. Demolition and installation of a new Coagulant chemical system. 4. Demolition and installation of a new Dechlorination system. 5. Additions and modifications to yard piping system. 6. Additions and modifications to electrical systems. 7. Additions and modifications to instrumentation systems. 8. Repair and reconstruction to existing facilities affected by the work and all work necessary to render the facility complete and operational.

Construction Duration: Work for the following project is schedule to begin on or about Monday, June 6, 2022 and estimated to complete on or around Tuesday, November 1, 2022.
Contractor: Pacific Infrastructure Corporation
Traffic Delays: None
Technical Contact: Project Manager, Stephen Fremming, ph: 209-,668-5417, sfremming@turlock.ca.us

City Project #20-009 - Well 38 Arsenic Mitigation and ICF Treatment

The scope of work includes demolition of an existing metal shed, wellhead modifications, piping, pressure filters, equalization tank, chemical storage enclosure, maintenance shed, underground sewer, storm drain, and water utilities, and site improvements including grading, paving, drainage facilities, site lighting, and landscaping.

Construction Duration: Work for the following project is schedule to begin on or about Tuesday, June 16, 2020 and estimated to complete on or around Thursday, September 1, 2022.
Contractor: Western Water Constructors
Traffic Delays: None
Technical Contact: Project Manager, Stephen Fremming, ph: 209-,668-5417, sfremming@turlock.ca.us

City Project #20-027A - City Wide Chlorination

The work consists, in general, of: constructing new chlorination systems at fifteen (15) active wells and three (3) water storage tank/pumping stations within the City’s water system.

Construction Duration: Work for the following project is schedule to begin on or about Wednesday, February 17, 2021 and estimated to complete on or around Wednesday, February 1, 2023.
Contractor: Clark Bros. Inc.
Traffic Delays: none
Technical Contact: Project Manager, Stephen Fremming, ph: 209-,668-5417, sfremming@turlock.ca.us

City Project #21-018 - Lander Ave Rehabilitation between D St and SR-99

The work consists, in general of: Install curb, gutter, sidewalk, driveways, vertical median curb, landscaping, fire hydrants, street lights, pedestrian activated crossing system, pavement rehabilitation, striping and signage, traffic signal modifications, and other associated work.

Construction Duration: Work for the following project is schedule to begin on or about Monday, August 22, 2022 and estimated to complete on or around Tuesday, January 31, 2023.
Contractor: George Reed
Traffic Delays: Lane Closures
Technical Contact: Randall Jones

City Project #20-039 - Traffic Signal Synchronization on E. Monte Vista A

The work consists, in general of: Remove and replace traffic signal equipment and other associated work. The work includes all necessary labor, materials, tools, equipment and any incidentals needed to perform the improvements as shown on the contract plans.

Construction Duration: Work for the following project is schedule to begin on or about Wednesday, February 1, 2023 and estimated to complete on or around Saturday, April 1, 2023.
Contractor: St. Francis Electric
Traffic Delays: None
Technical Contact: Randall Jones

City Project #20-038 - Signal Coordination on W. Monte Vista Ave, Golden

The work consists, in general of: Remove and replace existing signal controllers, and remove and replace an existing detection camera system and other associated work. The work includes all necessary labor, materials, tools, equipment and any incidentals needed to perform the improvements as shown on the contract plans.

Construction Duration: Work for the following project is schedule to begin on or about Wednesday, February 1, 2023 and estimated to complete on or around Saturday, April 1, 2023.
Contractor: St. Francis Electric
Traffic Delays: None
Technical Contact: Randall Jones

For more information or concerns about capital projects, please contact:

Engineering Division
156 S. Broadway, Ste. 150
Turlock, CA 95380
(209) 668-5520
engineering@turlock.ca.us
Monday - Friday, 9AM - 4PM






Icons made by Freepik from www.flaticon.com is licensed by CC 3.0 BY



Top